We are happy to share exciting news about the Tender process, and important dates pertaining to the Forbes Hall Upgrade and Expansion project.
The Hall as we know it will be upgraded and reconfigured to meet the current and foreseeable needs of our active community. As well, a large addition in the form of assembly space, storage, and service areas will be built. These changes have been made with significant community input, and much attention has been devoted to building sustainably whenever possible. We are thrilled that the community’s vision is unfolding!
Last week a huge milestone was reached: the tender documents were completed, delivered and distributed to a shortlist of four contractors on Friday, February 15, 2019.
Those four contractors attended a mandatory site viewing Thursday, February 21, 2019. Bids are due on Monday, March 11, 2019 and will be reviewed by TICA Directors, with a decision planned by Monday, March 25, 2019.
The start date for construction is set for Monday, May 1, 2019 however commencement will depend on the availability of the successful bidder. Based on this timeline, Forbes Hall could be turned over to the contractor as soon as Monday, April 15, 2019.
Plans are in place for the preparation of the hall for the construction including packing and storage, and relocation of the library and regular activities.
Anne-Marie Koeppen and a committee have been tasked with seeking alternative venues for regular users and activities to try to minimize interruption of activities during construction. More information about this will follow shortly.
We are at an exciting stage as Forbes Hall is on the edge of transformation! A large celebration is to be had before construction begins – stay tuned for more information about this event.