Chemainus & Thetis Terminal Upgrades

BC Ferries is about to award the contracts for the work on our terminals. The timelines are approximate, but will be very close to these dates:
Chemainus:
On site - January 3, 2017
Complete - February 15, 2017
Thetis:
On site - March 1, 2017
Complete - May 15, 2017
There are no expected disruptions/changes to our ferry service during both of these projects...
Regards
Keith Rush Route 20 FAC
Ph: 250-416-0013
Cell: 250-732-2766