Forbes Hall Expansion Update: Construction ~ September 10, 2020

Thetis Island Community Association

The calendar flipped to a new page, and here we are already in mid-September.  How did that happen so quickly? The hall is currently being sided, the final painting of soffits is underway, and with the metal siding arriving this week, the project moves forward towards the completion of the exterior. The outward appearance of Forbes Hall is changing before our eyes, and it is great to see something other than plywood and house-wrap.  The crew is so dedicated to doing good work, which is a true reflection on the capable abilities and leadership shown by Michel Poirier.

Excavation for the septic tanks has been completed with the new tanks installed.  It was important to get the tanks into the massive holes before the fall rains arrive.  All remaining work on the septic field can be completed later. The change in weather is going to come eventually, and getting most of the outside work done, as well as getting Forbes Hall to lock-up, is imperative.

All expenditures are weighed between the best choice for the years to come, logistics, design, and budgeted costs. Many of the early estimates of last spring now show increased material costs. These cost-increases all require reduced spending within Phases that have not yet begun, a reality to be contended with.  We are thankful that the majority of the build behind us, as these are not easy decisions.  The finalizing of materials that may seem inconsequential in the overall scheme of things, such as the type of doors, are given full consideration every step of the way. Timing is everything, as critical decisions are made for items where it makes the most sense to spend money on now, and changing their scheduled place within the original phasing, as sometimes changing the order creates a more efficient build.  All of this is part of the ongoing work that happens behind the scenes.  

Finishing the hall is now within sight, and the community’s support continues to be integral to the completion of the project. This past year and a half without Forbes Hall has weakened our social fabric. Having the hall available will be of great benefit to the community, and even with COVID-19 protocols in place, we will once again be able to gather.  

Tours continue to be held:

Please contact Ann Dickie, Teresa Moore, Tatiana Nemchin, Ellen Rush, or Don Sinclair if you’d like to book a tour on a weekend or late afternoon through September. Project Committee members will walk you through the hall and answer any questions you may have. 

Thank you to our crew, Michel, Chad, Liam, Mark, and Mike, we appreciate your days on the project and the professionalism of your work.

Forbes Hall Expansion Project - Moving Forward Thanks to Our Community.