Additional information about the construction schedule is now on the website. https://www.northcowichan.ca/EN/main/departments/engineering/construction-projects/chemainus-road-corridor-upgrade-project.html
Please continue to check the website for updates.
Construction Schedule Information:
• Construction will start mid-November 2019
• Phase 1 - Underground utilities construction will take 4 months - Mid-November 2019 to Mid-March 2020.
• Phase 2 - Above ground surface works will take 7 months - Mid-March to Mid-September 2020.
• Starting point (ie. Victoria St or Henry Rd) has not been identified yet, but more clarification to come.
• Construction will typically end at 5:30 pm each day and both lanes will be left open, unless unusual circumstances cause the crew to work longer to complete the task.
• Construction will typically not occur on weekends, unless unusual circumstances cause the crew to work longer to complete the task.
• There will be 1 to 3 flaggers on the work site during construction.
• Copcan Civil Ltd. Project Manager, Chris Laramee, will work with owners on Chemainus Road regarding access and parking on a daily basis. His contact information is (250) 754-7260 or claramee@copcan.ca.
Submitted by: Area G Director,
Lynne Smith